LICENSING SCHEDULE
The FERC licensing schedule requirements are shown in the table below and depict milestones in the Project licensing process.
| Activity of Milestone | Timeframe |
|---|---|
| Preliminary Permit Issued | April 2004 |
| Initial Consultation Document and Meeting | March 2005 |
| Study Planning and Field Studies | April 2005 - December 2007 |
| Scoping Process | March 2006 - March 2007 |
| Second Preliminary Permit Issued | August 2007 |
| Submit Draft License Application | April 2008 |
| Submit Final License Application | August 2009 |
| FERC Order Issuing New License | August 2011 |