LICENSING SCHEDULE

The FERC licensing schedule requirements are shown in the table below and depict milestones in the Project licensing process.

Activity of Milestone Timeframe
Preliminary Permit Issued April 2004
Initial Consultation Document and Meeting March 2005
Study Planning and Field Studies April 2005 - December 2007
Scoping Process March 2006 - March 2007
Second Preliminary Permit Issued August 2007
Submit Draft License Application April 2008
Submit Final License Application August 2009
FERC Order Issuing New License August 2011